What are the key takeaways?
- Funds are advanced in draws tied to verified progress, not all at once.
- Lenders track cost-to-complete closely; if the remaining budget exceeds the undrawn loan, the borrower must fill the gap.
- An interest reserve held back from the loan covers payments during construction but reduces the cash available for the build.
- The exit, usually sale of completed units or a conventional mortgage on the finished property, depends on finishing on time and on budget.
How does a draw schedule work?
Before the first dollar is advanced, the lender approves a budget and a schedule of draws tied to construction milestones, such as foundation, framing, lock-up, mechanical rough-in and completion. Each draw follows a similar cycle.
- Ask how long each draw takes to process and plan contractor payments around it.
- Ask whether interest is charged on the full commitment or only on funds advanced, since that changes the cost considerably.
- Ask what happens if a stage takes longer or costs more than budgeted.
- The borrower or builder requests a draw once a stage is complete, with invoices and a summary of costs to date.
- An inspector or quantity surveyor appointed or approved by the lender visits the site and reports on progress and costs.
- The lender confirms that the remaining loan is enough to finish the project, and that title is clear of unexpected liens.
- Funds are released, usually through the lawyer, less any holdback and fees.
What are the two kinds of holdback?
The word holdback can mean two separate things on a construction project, and it helps to keep them apart.
Statutory or lien holdbacks relate to provincial construction lien or prompt payment rules, which may require part of each payment to contractors and suppliers to be retained for a period. Whether and how that applies, including amounts and release timing, depends on the province and the contract, so confirm the details with a lawyer who handles construction matters.
Lender holdbacks are amounts the lender keeps back from a draw or from the overall loan, for example until occupancy, a final inspection or a specific condition is met. These are set by the loan agreement. Read prepaid interest and holdbacks for how lender holdbacks affect the cash you actually receive.
What do cost-to-complete and the quantity surveyor decide?
The single most important number in a construction loan is cost-to-complete: what it will take, in dollars, to finish the project from where it stands today. At every draw the lender compares it with the undrawn balance of the loan. If the cost to finish is higher than the money left, the loan is said to be out of balance, and the lender will typically expect the borrower to inject the difference before releasing more funds.
That is why a credible budget with a contingency matters so much at the start. Quantity surveyors or cost consultants review the budget before funding and track it through the build. Their reports protect the lender, but they also give the borrower an early warning when costs are drifting. Expect to pay for these reports, and ask about their cost up front.
What is an interest reserve?
During construction the property may produce no income, so some lenders set aside an interest reserve: a portion of the loan held back to cover interest payments for part or all of the build. It eases cash flow, but it is still borrowed money, and it reduces the amount available for construction.
The worked example uses the true cost calculator on a $900,000 Ontario construction loan with six months of interest held in reserve. The reserve is $49,500, and after fees and reserve the cash available on day one is $817,500. With fees, the effective annual cost rises from a contract rate of 11% to 16.3%. The calculation assumes the full amount is outstanding for the whole year; if interest is charged only on funds as they are drawn, the actual interest would be lower, which is exactly why the question in the draw section matters.
How do you exit a construction loan at completion?
Construction loans are designed to be repaid when the project is finished. For a custom home, that may mean a conventional mortgage once an occupancy permit is issued and the home is appraised. For a builder, it may mean selling completed units. For a rental building, it may mean refinancing with a longer-term lender once the units are leased.
Every one of those exits depends on finishing. Delays from weather, permits, trades or materials add interest and may push the project past the loan's maturity, triggering extension fees. Use the bridge exit planner to see what a few extra months would cost, and read when your exit runs late before construction starts. For projects that involve renovating an existing property for resale, fix-and-flip financing may be a closer fit.
What should you settle before you commit?
Get the budget, schedule and draw process in writing, and understand each fee: lender and broker fees, inspection and quantity surveyor costs, legal fees for each draw, and any renewal fee. Confirm permits, insurance (including builder's risk coverage) and warranty enrolment requirements in your province. Have a lawyer review the loan agreement with particular attention to cost overrun, default and completion clauses. The printable question list can help structure the conversation, and exit strategy planning can help you test the finish line.
What questions should you settle on a construction offer?
Construction loans fail most often on timing, so get the draw mechanics in writing. Ask how many draws there are, what triggers each one (a quantity surveyor's report, an inspection, a percentage of completion), how long a draw takes to fund after the request, and what happens to interest and holdbacks if the build runs late.
Ask whether interest is charged on the full commitment or only on funds advanced, whether unused prepaid interest is refunded, and what extension fee applies if the as-complete refinance or sale isn't ready at maturity. A delay of three to six months is common on residential builds; price it before you start, not after the framing goes up.
A $400,000 loan at 11.99% on a $700,000 as-complete value with six months of interest held back.
| Loan | $400,000 first mortgage12-month term, interest-only |
|---|---|
| Rate | 11.99%compounded monthly |
| Fees | $16,000lender 2%, broker 1%, other $4,000, deducted from the advance |
| Property | $700,000loan-to-value 57.1% |
| Clauses | 6 months' interest prepaid |
| Credit actually advanced | $360,020loan minus every deducted charge |
| APR on credit advanced | 16.67%Criminal Code s.347 limit: 35% |
| If repaid at month 3 | 42.87%fees spread over fewer months |
| All-in effective annual cost | 18.00% |
| Cost of the term | $63,960interest plus fees; $400,000 still owed at maturity |
| Analyzer verdict | Get it reviewed3 points to raise |
- serious If repaid early, the APR could pass 35% (42.9% at month 3)
- Check 6 months of interest ($23,980) prepaid from the advance
- Check Fees add 5.3% a year on top of the rate
Open this example in the commitment analyzer →Computed by this site's commitment analyzer (Criminal Code s.347, Interest Act ss.6, 8, 10). Illustrative terms, not an offer.
What does this mean for you?
- Ask whether unused prepaid interest is refunded if the build finishes early and you refinance.
- Match draws to your builder's schedule in writing; delays push the exit out.
- Budget for a late finish: model six extra months in the exit planner.
What do people ask most?
How do construction loan draws work?
The lender releases funds in stages after an inspector or quantity surveyor confirms the work is complete and the remaining loan can finish the project. Each draw may also involve a title check and a holdback.
What is cost-to-complete in a construction loan?
It is the estimated cost to finish the project from its current stage. If it exceeds the undrawn loan balance, the borrower may need to add funds before the next draw.
What is an interest reserve?
It is part of the loan set aside to pay interest during construction. It eases cash flow but reduces the money available for the build and is still repaid with interest.
Do private lenders fund owner-builders?
Some may, depending on experience, budget, equity and the exit plan. Expect detailed questions about who manages the build and how overruns would be covered.
This guide is general education for Canadians, not financial, legal or tax advice. Figures in examples are illustrative, not offers or market rates. Rules change; confirm current requirements with a licensed mortgage professional and a lawyer (or notary in Quebec).